Several risk response strategies are available. ( ) the risk simply gives another party responsibility for its management,it does not eliminate risk.
>
题目详情
问题题干
答案解析
相关问题
热门问题
最新问题
问题详情
Several risk response strategies are available. ( ) the risk simply gives another party responsibility for its management,it does not eliminate risk.
A、Avoiding
B、Mitigating
C、Accepting
D、Transferring
时间:2022-01-04 01:38
关键词:
答案解析
D
风险的转移是把风险责任转移到第三方,并没有消除风险。
相关问题
Workarounds are determined during which risk management process?()。
There are several ways to _____ this problem.
What are the several steps of Savings deposits
She mored_the city,where jobs are available
●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).
最新问题
Two types of anchor shackles which are currently available are().
Which four are types of functions available in SQL? ()
What are three primary activities in the cycle of building an enterprise security strategy?()
The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal ofthe plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies(),rransfer ,Mitigate.
The strategies for handling risk comprise of two main types:negative risks, and positive risks.The goal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies( ),Transfer ,Mitigate .
The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal Of the plan is to minimize threats and maximize opportunities. When dealing with negative risks,there are three main response strategies______,Transfer, Mitigate.
( )is especially valuable in locations where electrical connections are not available
●Several risk response strategies are available.(75) the risk simply gives another party responsibility for its management,it does not eliminate risk.
Several risk response strategies are available. ( ) the risk simply gives another party responsibility for its management,it does not eliminate risk.
setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?()