A、change the scope baseline
B、contact the customer to determine if the change adds value
C、call a meeting of the change control board
D、change the project’s objectives
A、change the scope baseline
B、contact the customer to determine if the change adds value
C、call a meeting of the change control board
D、change the project’s objectives