In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.


A、10

B、45

C、50

D、100

时间:2021-12-31 18:53 关键词: 专业英语 高级信息系统项目管理师

答案解析

B