某工程某月计划完成工程桩100根,计划单价为1.3万元/根,实际完成工程桩110根,实际单价为1.4万元/根,则费用偏差(CV)为()万元。
>
题目详情
问题题干
答案解析
相关问题
热门问题
最新问题
问题详情
某工程某月计划完成工程桩100根,计划单价为1.3万元/根,实际完成工程桩110根,实际单价为1.4万元/根,则费用偏差(CV)为()万元。
A、11
B、13
C、-13
D、-11
时间:2022-04-26 21:43
关键词:
商业经济行业技能考试
国家注册审核员(外审员)
建筑施工管理知识
答案解析
D
相关问题
boost的意思是:help or encourage to increase or improve
eloquent的意思是:fluent or persuasive in speaking or writing
A campus emergency ______ occur at any time of the day or night, weekend, or holiday, with little or no warning.
某打桩工程合同约定,某月计划完成工程桩120根;单价为1.2万元/根。时值月底,经确认的承包商实际完成的工程桩为110根;实际单价为1.3万元/根,则该工程的已完工作预算费用(BCWP)为( )万元。
Rent, economic(or pure economic rent) 经济租或纯经济租
最新问题
从事建筑工程活动的人员,要通过国家任职资格考试、考核,由( )注册并颁发资格证书
Mainly east 3 or 4 partly cloudy to overcast occasional rain()slowly south moderate or good.
()any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local quarantine officer must be notified immediately.
Should any case or suspected case of quarantinable disease,or any case of eruptive disease or any death be discovered,the local Quarantine Officer must be()immediately.
Masters are()solely responsible for all damages or accidents of whatever kind resulting from the navigating or handling of their vessels by day or by night.
If he is a common carrier,he is absolutely responsible to the owner of the goods carried ()any loss or damage to them unless caused by an Act of God or the Queen’s enemies,or the inherent vice in the goods themselves,or the negligence of the owner of the goods,or a general average sacrifice.
系统中雷达状态包括Unknown、Operational(or ON)、Failed(or OFF)、Detached。
管理(或非浮动)价格Administered(or inflexible) prices
Owners are to be responsible for loss of or damage to the goods or delay in delivery of the goods only in case the loss,damage or delay has been caused by the improper or negligent stowage of the goods.This means that().
The carrier is liable for loss of or damage to the goods or delay in delivery caused by fire,()the claimant proves that the fire arose from fault or neglect on the part of the carrier,his servants or agents.
别人在看