Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by ( ).


A、executive IT manager

B、project manger

C、change control board

D、project sponsor

时间:2022-03-16 05:44 关键词:

答案解析

C
项目变更可以由IT经理executive IT manager、项目管理者project manager、项目发起人project sponsor等任意项目干系人发起,但只有变更控制委员会change control board授权通过,所以选C。