● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.


A、(74)the project is ahead of its planned schedule

B、less work was completed than was planned

C、the cost overrun for work completed

D、the cost under-run of performance to date

时间:2022-03-15 23:13 关键词:

答案解析

B