● Which of the following is not part of a modern quality management concept?(74)(74)


A、Performance standard is zero defects

B、Quality must be inspected in

C、85% of failures occur because of the process, not the worker

D、Quality is a 4 cycle process – plan/do/check/act

时间:2022-01-05 16:13 关键词:

答案解析

B