问题详情

You notice that the elapsed time for an important database scheduler Job is unacceptably long. The job belongs to a scheduler job class and window. Which two actions would reduce the job's elapsed time?()


A、Increasing the priority of the job class to which the job belongs

B、Increasing the job's relative priority within the Job class to which it belongs

C、Increasing the resource allocation for the consumer group mapped to the scheduler job's job class within the plan mapped to the scheduler window

D、Moving the job to an existing higher priority scheduler window with the same schedule and duration

E、Increasing the value of the JOB_QUEUE_PROCESSES parameter

F、Increasing the priority of the scheduler window to which the job belong

时间:2022-01-04 16:11 关键词: 1Z0-060

答案解析

B| C