●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.(71)


A、Quantitative Risk Analysis

B、Qualitative Risk Analysis

C、Enterprise Environmental Factors

D、Risk Management Plan

时间:2022-01-03 17:23 关键词:

答案解析

B