()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.


A、Quantitative Risk Analysis

B、Qualitative Risk Analysis

C、Enterprise Environmental Factors

D、Risk Management Plan

时间:2022-01-03 17:23 关键词: 信息系统项目管理师综合练习 高级信息系统项目管理师

答案解析

B
参考答案:B